Production line readiness before automation went live
Context: A production line was scheduled for automation upgrades while operators had only classroom exposure to the new control philosophy, creating a high risk of downtime at go-live.
Advisory track: ERN defined the requirement, reviewed process stability and sequenced commissioning around acceptance criteria instead of vendor milestones.
Training track: Operators and supervisors practised start-up, fault handling and safe intervention on AR/VR modules and simulators in the Dojo before touching live equipment.
Observed results
- Operators certified before commissioning rather than after
- Fewer avoidable stoppages during ramp-up
- Standard operating procedures rewritten from actual practice